Presentation

T&M operates in the renewable energies industry. T&M began its experience in 2001, developing the construction of renewable energies works during the industry's summit in Spain, along 12 years, in which it developed and improved its executive processes. Transferring the knowledge acquired in these big companies, and modifying the work philosophy towards private clients we have been able to have our professionalism valued in a personal way in the market.
Our experience outside the renewable energies field is extensive. Ranging from the construction of parking lots, lower passageways and urbanizations, as far as the execution of road sections, highways, as well as railroads. This experience has been acquired during several positions of responsibility, from work supervision until the company’s direction.

Already in 2001 we began our experience in renewable energies, with the construction of wind parks. Works were subsequently developed in the construction of solar plants and biomass projects. T&M comprises a group of high specialized professionals with experience in works development management and in their know-how. T&M provides full management, meaning that it is present during the project development and its optimization, civil construction, and mechanical and electrical assembly; therefore, we can offer the possibility of turnkey construction and installation.
T&M provides its clients with clear benefits in works development: Administrative tasks reduction, process development agility, works development and their management, quality improvement, cost optimization, process time reduction, environment policies

assurance, and occupational risks prevention, all that assuring the client’s satisfaction level. In 2011 T&M decided to expand its areas of operation and jumped to Latin America, where currently the construction of wind farms is the company's main activity, counting on over 1,000 MW installed in Spain and over 500 MW in execution in Latin America, comprising civil works and electric infrastructure (medium voltage network). T&M has also worked in the construction of transforming substations, with their corresponding control buildings.

  • Sed fringilla mauris
    Wind Farm
    Los Cucuros
    Chile
    57 wind turbine, 102,6 MW
  • Solar farm
    Calama
    Chile
    150 MW
  • Sed fringilla mauris
    Wind farm
    Cristal
    Brazil
    39 wind turbine, 89 MW
  • Wind Complex
    Alto Sertão II
    Brazil
    230 wind turbine, 384 MW
  • Wind farm
    Cerro Negro
    España
    8 wind turbine, 16 MW